Permits for State land
0 notices open for comment · land use permits, leases, easementsNov 9, 2026
InfoAdministrative Order 360, August 4, 2025DNR publishes application status, timelines and decision rationale.AO 360
Apply
What do you want to do on State land
Timelines
How long it takes
Real public data
| Authorization | Target from a complete application | Public notice | FY2025 received / issued |
|---|---|---|---|
| Land use permit AS 38.05.850, 11 AAC 96.010 | 30 days from a complete application | At the department’s discretion | 422 / 433 |
| Lease AS 38.05.070, AS 38.05.075, 11 AAC 58 | 9 to 12 months from a complete application | 30 days | 169 / 194 |
| Easement AS 38.05.850 | 6 to 8 months from a complete application | 30 days | 39 / 52 |
OMB performance measures, DMLW · backlog 609 at the start of FY2022, 223 after FY2025