Permits for State land

0 notices open for comment · land use permits, leases, easementsNov 9, 2026
InfoAdministrative Order 360, August 4, 2025DNR publishes application status, timelines and decision rationale.AO 360

Apply

What do you want to do on State land

Start an application

Timelines

How long it takes

Real public data
AuthorizationTarget from a complete applicationPublic noticeFY2025 received / issued
Land use permit
AS 38.05.850, 11 AAC 96.010
30 days from a complete applicationAt the department’s discretion422 / 433
Lease
AS 38.05.070, AS 38.05.075, 11 AAC 58
9 to 12 months from a complete application30 days169 / 194
Easement
AS 38.05.850
6 to 8 months from a complete application30 days39 / 52

OMB performance measures, DMLW · backlog 609 at the start of FY2022, 223 after FY2025